The Rotary Club of Constantia played a key role in the building of the sports field at Grosvenor Primary School in Atlantis, creating a valuable space for sports and community events.
GROSVENOR SCHOOL SPORTS FIELD PROGRESS TIMELINE
December, 2024

Plan for field
January 18, 2025

Breaking ground
February 4, 2025

A total of 1,450 bags of cement have been laid out at Grosvenor Primary School. The next step is to mix the cement with water and begin the compaction process.
April 22, 2025

The development of the sports facilities at Grosvenor Primary School is well underway. The netball court has been successfully paved, and the soccer field is fully fenced, currently awaiting the installation of synthetic grass. In addition, a designated rugby area is being prepared for the laying of natural turf.
May 8, 2025


Learners starting to use turf.